Keesler AFB Community Hospital
Gulfport, Mississippi

Owner: GSA
Point of Contact: Shane Langley, W.G. Yates Construction
Project Completion: 2012
Commissioning Fees: $$59,190
Project Team: Josh Bhate, John Benedict & Rob Mayo
Project Involvement of BD&PS Project Team:
Commissioning Project Management, Commissioning Coordination of three Commissioning Specialist Subcontractors in HVAC, DDC Controls, Medical Gasses Systems and Standby Power Systems Automatic Transfer Switches. Commissioning Process Scheduling, Pre-Functional Checklist Review, Oversee Functional Testing, Identifying Deficiencies, Troubleshooting Deficiencies, O&M Manual Review, Systems Training Scheduling and Oversight.
Project Information:
The project is an addition to the existing Keesler Air Force Base Community Hospital. In total, the project added 143,000 square feet of space to the facility. The project's designer is RLF Architects of Winter Park, Florida. The contractor is Biloxi-based W.G Yates Construction.
Architect: RLF Architects
General Contractor: W.G. Yates Construction

Systems Commissioned by BD&PS:
  • HVAC
  • EMS Controls
  • Medical Gas Systems
  • Automatic Transfer Switches

 
Print Project Details